In Jira parent which has sub-tasks, the sub-tasks Estimated hour summary is not reflected to Jira

Taeseok Ou June 25, 2020

, the sub-tasks Estimated hour Sum is not reflected to Jira parent ticket automatically? along with Time logged

1 answer

1 accepted

0 votes
Answer accepted
Petter Gonçalves
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
June 26, 2020

Hello @Taeseok Ou

Welcome to the Atlassian Community!

Unfortunately, Jira Cloud does not have a functionality to sum the estimation of sub-tasks to their related parents. We have a feature request created with our development team to get it implemented:

Sum estimates from sub-tasks in user stories 

Feel free to vote and watch the suggestion to increase its priority and also receive notifications about any updates.

As a workaround, you can use third-party plugins. Here are some options:

  1. Use the calculated number field from Scriptrunner to properly sum the sub-task estimations. You can check some options using Scriptrunner checking the comments in this feature request.
  2. Sum it up! app provides an easy way to sum-up your estimations to the related parent issue.

Let us know if you have any questions.