Hi all,
In Active sprint, we have Story A with 2 sub-task as below:
=====================
Story A
Sub-task 1 (implement) -> Member B
Sub-task 2 (testing) -> Member C
=====================
We have quick-filter (assignee = Member C).
Current: When clicking on quick-filter, Sub-task2 will be displayed
Expect: When clicking on quick-filter, Sub-task1 and Sub-task2 will be displayed but Sub-task2 will in White-background and Sub-task1 will be in Gray-background
Business need: We need this because sometime when implement a sub-task1, we need to know status of sub-task2 and for knowing this, we MUST click on StoryA to see status of subtasks
Currently, we are using sub-task and filter tasks (belong to each members) by quick-filter (assignee = <name>).
The problem is: when choosing
Your quick filter specifically excludes sub-task 1. That's what you have built it to do.
You will need to create a quick-filter that includes the other sub-task instead of dropping it.