I am new to the Jira Admin scene but we are starting our migration of projects from our Cloud instance of Jira to our Server Instance v8.2.1
I tried searching the forums but couldn't find an answer. Is there a way to do this Natively? It looks like you can create a back up for a server but then you have to rebuild the server and restore from backup. We are looking to do multiple imports and not have to rebuild the server every time.
Thanks,
Doug
Hello,
There is no easy way to do it. There are two ways:
1. Create configurations of the projects manually and import issues by a CSV file.
2. Export Jira Cloud to a stage server and then use Configuration Manager or Project Configurator to migrate the required projects.