I have a new company managed project with a bunch of issues, epics created that existed in the backlog. When I changed the workflow to a new workflow, I can no longer see issues in the backlog. The issues are there when I click on issues, but they don't show up in the backlog to add them to a sprint.
Hey @Mike Piedmonte
Welcome to the community!
Have you updated the statuses in your workflow? If so, please verify if they're correctly mapped to the columns of your board. It is likely that the issues exists in statuses that are not mapped to any column of your board.
Please go to Configure Board > Columns section. If the statuses of your current workflow appear under the Unmapped status section, you can drag and drop them to the relevant columns. This should fix the issue.
Thanks,
Karan
Thanks, this fixed it!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.