Hi All!!
One of the PMs is using Jira work management for its projects.
He wants to add a milestone to be shown in Timeline section. He created a release and he associated it to one of the task in the project to see if its going to shows anything but it doesn't.
He followed the steps in this article but no luck https://support.atlassian.com/jira-work-management/docs/use-jira-work-management-for-project-management/
Is it possible? or should we move to Jira Software and buy an addon as big picture o WBS Gant?
Thanks in advance,
Ro
Hi @Rosana Casilli, it’s Tania from Planyway. Perhaps you’re open to trying other tools and wouldn’t mind giving a chance to Planyway. There, your PM can add milestones by simply clicking on the timeline in the corresponding line:
The milestones will be visible only in Planyway (not in Jira) and will be shown across multiple projects on one timeline in Planyway.
Feel free to ask any questions, I'll be happy to help.
Having the exact same problem, except I can't even access Versions/Releases where the articles say they are meant to be.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @[deleted] ! good morning!!
In my post there is a link to an article: https://support.atlassian.com/jira-work-management/docs/use-jira-work-management-for-project-management/
In that article there is a section named "Add project milestones using versions"
Although I can create versions, and add the affected version to issues, in Jira Work Management there is no way to see version progress like in Jira Software, on the other hand what the user needs is to see the milestone in timeline.
If there is no solution maybe I should move to a Jira Software Project and add a pluggin like WBS Gant or BigPicture...
Kind regards
Ro
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Some time after making this comment (and creating a whole bunch of projects including a Software project to test things) the ability to add 'Stories' appeared on the settings > issues > add dialog. I have then used WBS Gantt which lets you right click and convert a Story to a Milestone. I'm only by myself on this plan testing out the features, don't know if WBS Gantt would charge otherwise, not sure it would be worth it.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Travis! thank for your response. Maybe we will do an evaluation on both addons to see which is better for what the PMs are looking for
Regards,
Ro
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Rosana Casilli ,
I am happy to hear that you want to give a try to BigPicture or BigGantt.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.