How to close Parent Issues while all subtasks are already closed Edited

I cannot drag parent issue to make the status close

I am new here in Jira. I just created an issue with subtasks under a sprint.

Our team managed to closed all subtasks but not the parent issue.

is this a workflow related issue?

thanks in advance

 

2 answers

1 accepted

0 vote
Warren Levy Community Champion Sep 20, 2017

What is the current state of the parent ticket? It may need to be put "In progress" first.

Another way of trying to do this is, open the parent ticket. At the top there should be some buttons which relate to progressing it through the workflow, such as Start progress or Resolved which may help. If it is already in progress, there is usually a Workflow button which has the available options - what do you see there?

Thank you the quick response. i already tried to edit the said parent ticket but there is no option to edit the status.

my workflow looks like this:

New - In progress - Code Review - QA - Closed

and for your information this parent task came from my previous sprint carried over to my active sprint.

Warren Levy Community Champion Sep 20, 2017

Hi Jeffrey

You didn't say what state the parent is in currently.

I asked that you open (not Edit) the parent, so the top looks vaguely like this

 

Picture0006.jpg

In my example, the ticket is In Review and there are buttons for Resolved and Failed Review. You won't have those options, but you may have some to help you progress it. Possibly attach a similar screenshot of your parent ticket so we can see where it is

I attached a screenshot below. i cannot locate the open from this view.Parent issue.JPG

Warren Levy Community Champion Sep 20, 2017

Okay, with the parent ticket showing in the right hand pane, click on the key (MI-26 in your screenshot). You'll notice it's shown in blue because it's a hyperlink - this will then open the ticket to the stage that I would like to have a screenshot of

Wow it works! thanks a lot bro!

is there any way to automate this? I mean, once all subtasks are closed its automatically close the parent task?

 

Parent issue - closed.JPG

Warren Levy Community Champion Sep 20, 2017

I'm sure I've seen that functionality before - as you close the last subtask, Jira asks if you want to close the parent as well. But I'm a Scrum Master now and haven't used Jira as a developer for a while, so not sure if it still exists or how to get it working

0 vote
Suhas Patil Community Champion Sep 20, 2017

Check if you have a transition from current status of an issue to the closed status. You might need to transition issue to another status before closed. 

Suhas Patil Community Champion Sep 20, 2017

You also need to check if there are any specific condition on the workflow transition. You can do this by going into workflow edit mode.

Is it safe to edit the current workflow while we have ongoing sprint?

if not, is it safe to change the workflow scheme in the middle of the sprint?

 

thanks in advance!

Suggest an answer

Log in or Join to answer
Community showcase
Sarah Schuster
Posted Jan 29, 2018 in Jira

What are common themes you've seen across successful & failed Jira Software implementations?

Hey everyone! My name is Sarah Schuster, and I'm a Customer Success Manager in Atlassian specializing in Jira Software Cloud. Over the next few weeks I will be posting discussion topics (8 total) to ...

3,296 views 14 20
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot