July 2, 2019

I need to know how many days a task took to get ready

1 answer

1 accepted

0 votes
Answer accepted
Milan Chheda [INFOSYSTA]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
July 2, 2019

You can use ScriptRunner add-on to write a simple script and show the number of days in a custom scripted field.

 

Here you can find an example script too: https://community.atlassian.com/t5/Jira-questions/ScriptRunner-find-number-of-days-between-two-custom-date-fields/qaq-p/596551