Hi, I am new to Jira and I would like to add a time estimate to my issue. I am able to log time and change the time remaining but I cannot find any dialog to add a time estimate for this bug?

 

I have found guides for the previous UI but since this has changed I cannot find the required dialog. I think I am missing an enable function but cannot find it.

 

Has anyone had a similar issue and if so how did you get round it?

1 answer

1 accepted

1 vote
Accepted answer

Fixed.

 

Navigate to Project settings > Fields > Actions > Edit Fields > (find field you want - i.e. time tracking) > screens > choice project you want it on.

To log work, you must click into the task ( not just pop up on board ) > click the + beside 'time tracking' and log it there.

I followed all steps and it did not work. Not sure why cant this basic feature be more stright forward.

After following all the steps I am still unable to edit time estimation for the task.

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Oct 16, 2018 in Jira

Looking for anyone who made the switch to Data Center

The Jira Marketing team is putting together an ebook on migrating to Data Center. We're looking for pro tips on how you staffed your project team and organized your Proof of Concept. Share yo...

1,074 views 11 10
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you