How to Copy aggregate value of customfields in to third customfield?

I have three fields

  • Task Start Date/Time
  • Original Estimate
  • Expected End Date/Time

I want value of "Expected End Date/Time" as "Task Start Date/Time + Original Estimate"

 

Can some one please tell me how is it possible?

 

JIRA Version 6.x

2 answers

1 accepted

0 votes
Accepted answer

There will be several ways for it.

1) Scripted custom field.

2) Script to calculate the "Expected End Date" on the post function of transition itself.

Hi Jayesh, Do you have any examples for this? Thanks

Hi Pushpkant, I don't have exact example for your query, but with the help of post function script it can be easily achieved. Cheers, Jayesh

forget to mention this activity has to be done at the time of Issue Creation

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Nov 27, 2018 in Portfolio for Jira

Introducing a new planning experience in Portfolio for Jira (Server/DC)

In the past, Portfolio for Jira required a high degree of detail–foresight that was unrealistic for many businesses to   have–in   order to produce a reliable long-term roadmap. We're tur...

2,571 views 15 21
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you