How to Copy aggregate value of customfields in to third customfield?

I have three fields

  • Task Start Date/Time
  • Original Estimate
  • Expected End Date/Time

I want value of "Expected End Date/Time" as "Task Start Date/Time + Original Estimate"

 

Can some one please tell me how is it possible?

 

JIRA Version 6.x

2 answers

1 accepted

There will be several ways for it.

1) Scripted custom field.

2) Script to calculate the "Expected End Date" on the post function of transition itself.

Hi Jayesh, Do you have any examples for this? Thanks

Hi Pushpkant, I don't have exact example for your query, but with the help of post function script it can be easily achieved. Cheers, Jayesh

forget to mention this activity has to be done at the time of Issue Creation

Suggest an answer

Log in or Join to answer
Community showcase
Sarah Schuster
Posted Jan 29, 2018 in Jira

What are common themes you've seen across successful & failed Jira Software implementations?

Hey everyone! My name is Sarah Schuster, and I'm a Customer Success Manager in Atlassian specializing in Jira Software Cloud. Over the next few weeks I will be posting discussion topics (8 total) to ...

2,907 views 12 18
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot