How does Jira Portfolio calculate duration, minimum work package size doesn't seems to be considered

A ridiculously small items in my portfolio (180 story points) takes, in length, about half of an items with 2160 story points.

I only have 1 team defined and no releases exist as of now.

I tried to play with the "Minimum Work Package Size" parameter and put it at 60 (so, 3 sprints to do the small items) and nothing seems to change, even recalculating does nothing.

Any ideas? 

 

1 answer

I still don't understand why, but it seems that when a high level item in the portfolio has child issues and the other not, this has an influence.

Suggest an answer

Log in or Join to answer
Community showcase
Sarah Schuster
Posted Jan 29, 2018 in Jira

What are common themes you've seen across successful & failed Jira Software implementations?

Hey everyone! My name is Sarah Schuster, and I'm a Customer Success Manager in Atlassian specializing in Jira Software Cloud. Over the next few weeks I will be posting discussion topics (8 total) to ...

3,321 views 14 20
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot