How does Jira Portfolio calculate duration, minimum work package size doesn't seems to be considered

A ridiculously small items in my portfolio (180 story points) takes, in length, about half of an items with 2160 story points.

I only have 1 team defined and no releases exist as of now.

I tried to play with the "Minimum Work Package Size" parameter and put it at 60 (so, 3 sprints to do the small items) and nothing seems to change, even recalculating does nothing.

Any ideas? 

 

1 answer

This widget could not be displayed.

I still don't understand why, but it seems that when a high level item in the portfolio has child issues and the other not, this has an influence.

Suggest an answer

Log in or Sign up to answer
Atlassian Summit 2018

Meet the community IRL

Atlassian Summit is an excellent opportunity for in-person support, training, and networking.

Learn more
Community showcase
Posted Wednesday in New to Jira

Are you planning to trial, or are currently trialling Jira Software? - We want to talk to you!

Hello! I'm Rayen, a product manager at Atlassian. My team and I are working hard to improve the trial experience for Jira Software Cloud. We are interested in   talking to 20 people planning t...

128 views 2 0
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you