How change the Status 'Estimated' Not Specified after work in the task without story points

Igor Tumarkin December 4, 2018

Hello all,

1. The person started working in a case.

2. This case was not estimated before.

3. The person logged his working time.

4. Jira shows in the 'Estimated:' just 'Not Specified'.

Screen 1.png

5. I added the story points, but the result is the same.

How can I show a normal (3 lines with 3 colors) representation?

Screen 2.png

Thanks in advance

Igor

1 answer

1 accepted

0 votes
Answer accepted
Alexey Matveev
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 4, 2018

Hello,

You need to add the time tracking field to the edit screen and set the Original Estimate value, not Story Points.

Igor Tumarkin December 5, 2018

Hello Alexey,
Thank you very much, it works now :-)
Regards,
Igor

Alexey Matveev
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 5, 2018

You are most welcome!