Greenhopper: Subtask time should be subtracted from parent task?

Hello,

during our Sprint Planing 2 phase we usually add several sub-tasks to a story/task in the current sprint.

Is is possible that the time we estimate for the sub-tasks is getting subtracted from its parent task, so that the time for the sprint does not increase if we add sub-tasks?

Just for clarification: I first add several sub-tasks to a task, and will some minutes later add time estimations to them. Can those time estimations be subtracted from the parent task?

1 answer

This is not possible. If you pull up the task/story in the planning/rapid board you will see what the total estimate for all the tasks are. Is it possible that some of the tasks have got orphaned/unlinked to the sprint?

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published Monday in Jira Software

How large do you think Jira Software can grow?

Hi Atlassian Community! My name is Shana, and I’m on the Jira Software team. One of the many reasons this Community exists is to connect you to others on similar product journeys or with comparabl...

382 views 4 10
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you