Dynamic Date is not working in The Scheduler

Susan Hauth _Jira Queen_
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
May 9, 2019

Our field "Implementation date and time" (date/time picker) we want to set it 5d 18h from the creation date of the scheduled issue.

However we're getting really weird dates set based on that:

The issue that was created from the scheduler ended up with this weird date:

image.png

THere were no updates to the Implementation Date and Time that's what the scheduler put in.

Here's how the Implementation date and time field was configured in The Scheduler:

image.png

2 answers

0 votes
Łukasz Modzelewski _TTPSC_
Marketplace Partner
Marketplace Partners provide apps and integrations available on the Atlassian Marketplace that extend the power of Atlassian products.
May 20, 2019

Hi @Susan Hauth _Jira Queen_ ,

Take a look at the example next to input "m" is treated as month, if you would like to use minutes use "min"

Please check if thats the case :)

Cheers,

Łukasz

PS. Our recommended support channel is our Customer Portal: https://psc-software.atlassian.net/servicedesk/customer/portal/10 

0 votes
Deleted user May 9, 2019

Hi there,

I just wanted to confirm if you're talking about "Automation for Jira", or "The Scheduler"? Since this question was fired under Automation for Jira: https://marketplace.atlassian.com/apps/37456/the-scheduler?hosting=cloud&tab=overview.

Susan Hauth _Jira Queen_
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
May 10, 2019

Oops....got the wrong tag...I have updated it thanks...