Documentation for Evidence Based Scheduling according to GHS-1656

Anders Persson October 5, 2011

According to the Issue GHS-1656 "Evidence Based Scheduling" is implemented in versino 4.1 and I would like to understand how to use it.

What I need is some way to predict the unscheduled items release date, e.g. which SPRINT they will be done according to the current Velocity estimate.

Today I use "Statistics" and set the Capacity to, for example, 20 Story Points. Then Greenopper shows, by adding a horizontal line with information about the Story Points, which use cases wil be possible to include in the first SPRINT. I would like to have indications for several SPRINTs. Just adding yet some more horizontal lines would help. Can I do that?

Regards

Anders

1 answer

1 accepted

0 votes
Answer accepted
Anders Persson November 3, 2011

I solved my problem by counting the number of SPRINTs left until the release and multiply it with our predicted velocity. Then I added that as our Capacity and got an estimate of what will be possible to include in the Release. Maybe not exactly what I wanted but good enough for my purpose.

Suggest an answer

Log in or Sign up to answer
TAGS
atlassian, atlassian community, loom ai, atlassian loom ai, loom, atlassian ai, record recaps of meetings, meeting recaps, loom recaps, share meeting recaps,

Loom’s guide to great meetings 📹

Join us to learn how your team can stay fully engaged in meetings without worrying about writing everything down. Dive into Loom's newest feature, Loom AI for meetings, which automatically takes notes and tracks action items.

Register today!
AUG Leaders

Atlassian Community Events