How could I configure GreenHopper to display subtasks in the backlog/sprint and to be able to edit estimates?
Is it possilbe to calculate parent issue estimate (story points) based on subtasks estimates?
The subtasks do not display in the backlog directly, they are shown in the Sub-Tasks tab on the detail view that appears when you click on the issue. You can see what the tab looks like in a screenshot from the release notes.
You can enter the estimate for the sub tasks when you create it from the sub-tasks tab.
There is currently no way to roll up a story point estimate to the parent issue. For more discussion about estimation you might like to check out an answers post on the topic.
Thanks,
Shaun