DR setup in jira 6.4 Edited

We are using JIRA 6.4 (without data center ).below are some requirements from our team.

So we request you please provide some steps for DR setup.

Requirement:-

  • Production and DR always be in sync.
  • At any time prod goes down DR can start without affecting the end user.
  • Once we do the reindexing in production/DR no need to do the same steps on another server.

 

1 answer

0 vote

You need Data Centre to get this.

The closest you can get without DC is a warm standby - a stopped Jira install on another machine, replicating the database to the backup, and synchronising some of the home directory.  When you have a problem, you shut down production (if it's running), start the other one and run a full re-index and repoint DNS.

Suggest an answer

Log in or Join to answer
Community showcase
Sarah Schuster
Posted Jan 29, 2018 in Jira

What are common themes you've seen across successful & failed Jira Software implementations?

Hey everyone! My name is Sarah Schuster, and I'm a Customer Success Manager in Atlassian specializing in Jira Software Cloud. Over the next few weeks I will be posting discussion topics (8 total) to ...

3,314 views 14 20
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot