When I mark a sprint complete full of 100% green done tasks most of which were completed before the end of the sprint, the tasks are considered "Open" and aren't moved. I tried all the done statuses we have available and none of them work.
How can I fix this.
Hi Benjamin - Welcome to the Atlassian Community!
While the tasks might be marked as Done, they are not considered to be completed on a Sprint board unless they are in the last column of the board (far right) regardless of the status.
Hey Benjamin,
It sounds like Jira isn't recognizing your completed tasks properly when closing the sprint. This usually happens due to one of the following reasons:
1️⃣ The "Done" status isn't in the last column of the board
2️⃣ The workflow isn't correctly configured for "Done" statuses
3️⃣ Tasks don’t have a resolution assigned
4️⃣ Try closing the sprint from the backlog
🔍 Recommended Fix:
First, check if "Done" is correctly mapped in the board settings. If everything looks good there, review the workflow and resolution settings.
Let me know what statuses you're using and how your workflow is structured if the issue persists—I’d be happy to help further!
Hope this helps! 🚀
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Candelaria Pereira -- Welcome to the Atlassian Community.
What is the source of the content you posted?
If this is from an automated / bot source, please review the community guidelines regarding disclosure of such sources in the text of your post:
https://community.atlassian.com/t5/custom/page/page-id/rules-of-engagement
Kind regards,
Bill
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.