Want to flag a sub-task for a story because it is blocked. Do I need to Flag the story or can I flag just the sub-task?
Hello Jason,
Welcome to Atlassian Community!
The flag feature is nothing but a custom field that receives a value ("Impediment") and it adds a red flag to the issue in the board view.
That been said, the answer is yes! You can add flags to a sub-task issue without needing to add it to its parents.
To do it in the backlog view, find the parent of the sub-task issue and click on it. Then, click in the sub-task at the right panel opened (detail view) and click in Add Flag:
To do it in the active Sprint view, you just need to right-click in the sub-task card > Add flag:
Let me know if you still have any questions.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.