Can I automate a sub-task when another sub-task status is labeled done?

Ankur Amin February 19, 2025

IMG_9931.jpgI have an impediment with a sub-task automated when a request comes in. What I was wondering is if the status of that sub-task gets set to Done, can another sub-task be automatically created? 

Think of it like, a request comes in, Request Received sub-task is auto created. Once the team member goes into that sub-task and flips that status do Done, I would need a another sub-task called develop report to be automatically created. Thank you!

1 answer

1 vote
John Funk
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
February 19, 2025

Hi Ankur,

Yes, you can do that, but you will need a second automation rule. It would be based on an Issue Transitioned trigger. Add any Conditions as needed and then an action to create a new issue. 

 

Ankur Amin February 19, 2025

Would you be able to share what I need to do to get that started? Thank you!

Ankur Amin February 19, 2025

I have three boards for three different departments, will it cause issues let's say for boards 1 and 2 if I wanted things done for board 3? Thanks!