Burndown report page in JIRA not showing all the issues/defects that are in the sprint

Jyoti Bisoi August 29, 2019

Evidence1.PNGEvidence2.PNGWe are using story points for burndown report. Noticed that we have total around 100 defects with story points as estimation added to the current sprint, But only 75 are reflecting in burndown. So while we should get sum of all 100 story points in report to burn down we got less(around 75).

 

We tried to remove and re-add sprint value but it didn't help and not added to burndown.

 

Sprint report is fine and reflecting all 100 defects FYI. Any help appreciated.

 

Thanks,

1 answer

0 votes
Ignacio Pulgar
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 30, 2019

Hi Jyoti,

There's a bug that might be affecting you:

https://jira.atlassian.com/browse/JSWSERVER-13996

The workflow set for Defect issue type might count with a post-function on its Create transition for auto-transitioning it on creation. Is that the case?

Regards