Auto creation of five sub-tasks should create, when the parent issue is created.
suppose i have 5 different groups as group A, group B, group C ,group D and Group E
When the five sub tasks are created automatically each sub task should assign to single group such as Subtask1 should assign to groupA, Subtask2 should assign to GroupB, Subtask3 should assign to GroupC, subtask4 should assign to GroupD, subtask5 should assign to groupE, can we acheive this by using only Scriptrunner plugin?
You will need an addon. I use Automation for Jira but there are any number of addons - Scriptrunner, Power Scripts, recurring tasks, etc.
Hi @srikanth,
@Jack Brickey is correct, if you are using Jira server, I'd recommend trying Quick Subtasks for Jira, as it's a free add-on so it should be an easier process to get installed and start using.
Just my two cents.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
https://library.adaptavist.com/entity/create-a-subtask-and-link-to-parent-issue-in-jira has a script that creates a sub-task (you can remove the bits that create a link though, I personally think that's a waste of time because a sub-task is already part of the parent)