Associating sub-task to task

Is it possible to associate a sub-task to multiple tasks/issues ie, can a sub-task have multiple parents ?

2 answers

1 accepted

1 vote
Accepted answer
No. A sub task can only have one parent, by definition. You can use issue links to connect issues when the relationship is not parent/child
0 votes
No. A sub task can only have one parent, by definition. You can use issue links to connect issues when the relationship is not parent/child

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Nov 27, 2018 in Portfolio for Jira

Introducing a new planning experience in Portfolio for Jira (Server/DC)

In the past, Portfolio for Jira required a high degree of detail–foresight that was unrealistic for many businesses to   have–in   order to produce a reliable long-term roadmap. We're tur...

2,712 views 17 21
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you