Should Burnup report include the Story Points from sub-tasks?

Mikhail Davydov July 24, 2019

Hi All,

 

I find the new Jira Burnup report to be better than previous Burndown, as it feels better when you are going up :D

However, at this point, Burnup includes only the Story Point Estimates from Tasks, but not from Sub-Tasks, which makes Sub-Tasks estimates to be useless.

Is there any way to make Burnup chart to include Sub-Task Estimates?

 

Best regards,

Mikail

3 comments

Comment

Log in or Sign up to comment
Warren
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
July 24, 2019

Hi @Mikhail Davydov 

Generally in Scrum, parent tickets (Tasks etc.) will have an estimate in Story Points and sub-tasks will have an estimate in hours. You can choose to either burndown or burnup of the sum of the hours on all sub-tasks or the sum of story points on all parents.

If a Task is broken down into sub-tasks, you haven't achieved any value until all sub-tasks are complete, which is why story point burndown or up is based on the parent only.

Like Mikhail Davydov likes this
Mikhail Davydov July 24, 2019

Thank you for the clarification!

Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
July 24, 2019

No, it should not include sub-task estimates.

When you're doing Scrum, the burn-down and burn-up are a measure of what you said you were going to do when you went into the sprint.  You commit to doing a set of issues, and the question for the burn reporting is "is what you committed to done or not"?  There is no partial done, your product owner does not care if 0%, 1% or 99.99% of the sub-tasks are done, the issue is not done until the story is done, and that's why burn reports should only look at the story level.

(Internally, a team may well find estimates on sub-tasks might tell them something useful during a sprint, but because the burn reports are for reporting on completion of stories committed to, the sub-tasks are irrelevant)

Like Mikhail Davydov likes this
Mikhail Davydov July 24, 2019

Thanks for a great explanation! All is clear now.

Danut M _StonikByte_
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 12, 2019

Hi @Mikhail Davydov ,

 

In the latest version of our Great Gadgets plugin, the sprint and release burndown gadgets have an option to include sub-tasks, which you could use to achieve what you want.  The plugin is available for both Jira Server (https://marketplace.atlassian.com/apps/1218777/great-gadgets-for-jira-server?hosting=server&tab=overview) & Jira Cloud (https://marketplace.atlassian.com/apps/1216564/great-gadgets-for-jira-cloud?hosting=cloud&tab=overview). 

 

Danut.

Like Mikhail Davydov likes this
Mikhail Davydov August 12, 2019

Thank you Danut!
I probably will check it out after testing the flow suggested above.