Can I create a "cancelled" status that does not interfere with reports (burnup, burndown, etc...) in my project?

1 answer

0 votes
Walter Buggenhout
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
March 21, 2024

Hi @Camila Gomes,

Yes, sure. If you don't want it to impact your reports, you should not map it to a column on the board. If you do map it to a board column, it should not be the rightmost column of the the board to make issues disappear from future sprints. And if you don't do that, your issues will be considered incomplete by the time you close your sprint and - because of that - return to the backlog.

Hope this helps! 