if we use story points for estimation is there any way to get burndown prior to a story being resolv

we have a custom workflow that has in progress, QA, ready to release and Done.  i want ready to release to show as burndown on our chart.

1 answer

0 votes
Tarun Sapra Community Champion Jun 16, 2017

Hello Aimee,

On the scrum boards burndown is taken into account when the issue moves into the "right-most" column of the board, thus if you put the "ready to release" as the right most column then it will account for the burndown.

And once you have the burndown, you can bulk update the issues to "done" with resolution.

awesome! i will try it!  thank you

one more question...epics seem to be treated like any other issue vs a direct hierarchy.  while issues are grouped under an epic, when you start progress on an epic it lands on a board.  just wondering if i should even bother to put them through workflow?  thanks!

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Apr 22, 2018 in Jira Software

How-to setup a secured Jira Software 7.9.0 on Ubuntu 16.04.4 in less than 30 minutes

...PermissionsStartOnly=true User=www-data Group=www-data ExecStart=/opt/jira/bin/startup.sh ExecStop=/opt/jira/bin/shutdown.sh TimeoutStartSec=120 TimeoutStopSec=600 PrivateTmp=true [Install] WantedBy...

2,079 views 14 13
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you