Why is my burndown non-linear?

logman
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 15, 2019

There is a non-linear line. How can this be explained? Can I trust this burndown?

Non_linearBurndown.png

1 answer

1 vote
Jack Brickey
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
October 15, 2019

Hi @logman , first this isn't a burndown chart it appears to be a Version report.

In this report there are a number of things being charted. The blue line will not be linear I think as it is driven by actual work and will vary as to predict the actual completion date. At least I believe this is the case.

Here is an article that might be helpful - Version-Report 

Suggest an answer