In my project, when I hit 'Create Sprint' it creates a sprint for another Projects board.. We did not link these two boards together? not sure how this happened? Anyone know what to do ?
Hello,
Please note that: "Sprints are not tied to an Agile board. They are tied to the issues and will be available across boards if the boards have filters that uses the same issues."
Please also review the statements and comments at: https://community.atlassian.com/t5/Jira-Software-questions/Sprint-appears-to-be-owned-by-a-different-board-from-the-one/qaq-p/200963
If still an issue, please list the steps on how to duplicate the behaviour.