Sprint days remaining is showing the wrong number

Regis_Zanandrea April 23, 2018

Hi,

 

I started a new sprint that have three weeks, but is showing two weeks on "days remaining".

 

Anyone having the same issue?

 

Captura de Tela 2018-04-23 às 2.18.51 PM.png

1 answer

1 accepted

1 vote
Answer accepted
Fazila Ashraf
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
April 25, 2018

Hi @Regis_Zanandrea

I see the confusion here.. ;)

Remember: 1 week = 5 days in JIRA (default.. unless you change it site wide)

So 3w=15d and what you see is 14d and that is fine.. is n't it?

Regis_Zanandrea April 25, 2018

Oh, Now its make sense. Thanks @Fazila Ashraf

Suggest an answer

Log in or Sign up to answer