On subtask there is no burndown can we change this?

Bongani Hermans July 17, 2019

Is this possible with a config?

1 answer

0 votes
Warren
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
July 17, 2019

Hi @Bongani Hermans 

When you say there is no burndown for sub-tasks, I'm assuming you've set up your Jira to show burndown of Story Points? If so, you may want to change it to burndown hours, as long as you have an hours estimate for each sub-task. To do this, click on the 3 dots in the top right hand corner, then select the Estimation tab. From the dropdown, choose Original Time Estimate and choose the lower radio button

Bongani Hermans July 17, 2019

Hi @Warren  

Our Jira setup  is not set to show burn-down of story points , There is  no option for selecting estimation Tab.

Kindly please advise.

Regards

Warren
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
July 17, 2019

Hi @Bongani Hermans 

You need to be at least a Project Admin to do this, and what I'm describing is for the cloud based version, although the server version should be similar.

Go to Board settings

Screenshot_2.jpg

 

then click on Estimation

Screenshot_3.jpg

Bongani Hermans July 19, 2019

Hi @Warren Levy

Thanks - much appreciated , It worked.