Hi!
I want to Log worked hours directly from the plan view in Jira.
For example, I can edit the Estimate (Original Estimate) field from here, see the progress (remaining estimate), but I can't log hours. For this I have to go into each issue and log them. Is there a way to log hours from this view?
Hello @Matias Rodríguez Alonso
That is not possible.
You can see and edit the Original Estimate field because it is a single value field, and there is only one Original Estimate per issue.
A Work Log is multi-field entity, and there can be multiple Work Logs associated with an issue.
Additionally, making modifications through the Plan does not immediately apply those modification to the underlying issues. You have to review changes made in the Plan and commit them to the issues.
For both of these reasons, logging work through the Plan interface does not align with its current capabilities.