Is there any way to configure time spent in Sprint Health gadget (work complete)

As described here, the Sprint Health gadget will not reflect the progress from work logged in the 'Remaining Estimate' and 'Time Spent' fields in JIRA.

My agile board estimation is configured to use "Original Time Estimate", and Time Tracking is set to use Remaining Estimate and Time Spent. As I can see on link above, the Sprint Health plugin will never show work complete (right?).

Is there any way to see the work complete without changing the Estimation Statistic?

1 answer

As far as I know, only way to display the work complete is by changing the estimation statistic (to issue count).

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Feb 26, 2019 in Jira Software

How to prevent the propagation of unused project schemes, workflows & screens in Jira software

Atlassian ranks project attributes as the third most important factor impacting performance in the category of data. It’s not surprising, since project attributes are precisely the rules used to ma...

649 views 0 7
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you