Is there any way to configure time spent in Sprint Health gadget (work complete)

As described here, the Sprint Health gadget will not reflect the progress from work logged in the 'Remaining Estimate' and 'Time Spent' fields in JIRA.

My agile board estimation is configured to use "Original Time Estimate", and Time Tracking is set to use Remaining Estimate and Time Spent. As I can see on link above, the Sprint Health plugin will never show work complete (right?).

Is there any way to see the work complete without changing the Estimation Statistic?

1 answer

As far as I know, only way to display the work complete is by changing the estimation statistic (to issue count).

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Mar 28, 2018 in Jira Software

Can a company’s culture make or break agile adoption?

Can a new-to-agile team survive and thrive in a non-agile culture? If so, what advice would you give to those trying to be agile in a non-agile culture? What's the key(s) to success? Share your thoug...

17,661 views 18 20
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you