Is there a way to configure agile board cards to show estimate effort in d, and not convert to w?

Is there a way to configure agile board cards to show estimate effort in d, and not convert to w?

2 answers

1 accepted

0 vote

Hi Lynn,

Basically, this follows the settings of Time tracking. You need to change the "Time estimates will be displayed in the following format" from pretty to days to make this work.

I hope this helps.

Cheers,

Clarissa.

Thank you so much. This did answer my question.

As a JIRA admin, you'd need to go to the Administration menu / System / Time Tracking

https://confluence.atlassian.com/display/JIRA063/Configuring+Time+Tracking

 

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published May 21, 2018 in Jira Software

How large do you think Jira Software can grow?

Hi Atlassian Community! My name is Shana, and I’m on the Jira Software team. One of the many reasons this Community exists is to connect you to others on similar product journeys or with comparabl...

1,233 views 10 18
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you