In rapid board (as a scrum master) I like to be able to move a ticket from "To Do" to "In Progress"

I am in rapid board and I like to be able to move tickets into In Progress. Sinc eI am the scrum manster and not the assignee, I am not allowed to move the ticket into In Progress. Is there a way to allow this? It is a common scenario when in daily standup people report that they have already started working on something but forgotten to push the In Progress button.

1 answer

1 accepted

2 votes

That is driven by the workflows. The only option is to modify the workflow and provide you the permission to execute that operation. Bt default, only assignee can start the progress.

Yes, you can allow it to a role, then make sure you are in that role. I tend to have a role of "project admin" simply so we can nominate several owners of any project and give them all access to maintain users, versions and components, plus do some things in the workflow that most users wouldn't get.

Can I provide that permission to the Project Admin? Is there such an option?

Suggest an answer

Log in or Join to answer
Community showcase
Teodora [Botron]
Published Thursday in Marketplace Apps

Jira Inferno: The Nine Circles of Jira Administration Hell

If you spend enough time as a Jira admin - whether you are managing a single, mid-sized instance, a large enterprise one or juggling multiple instances at once - you will eventually find yourself in ...

247 views 0 11
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot