Hello Team,
I have Quick question to ask.
I am bit confused with graph in Sprint report
image2015-8-4 12:58:21.png
Can any one of you please explain the above graph,
1)what does Red line,Green line and Grey Line Indicate here.
2)why is the Red line started from the top? and why is it decreasing ?
3)what does Grey line indicate,why is it started from Top and Gradually decreased
Thanks,
Yogashree.M
Guide line means the optimal way the sprint progresses. The Estimate decreases consistently, stabilizes at few instances and then reach zero at the end of the sprint (last day of sprint)
Redline - remaining values.
Grey - provides guideline for the progress
Greenline - progress of the sprint
It provides the correct data after the sprint completion
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
We are using 6.3.6 version, and also i was talking about Green Line.
what does green Line indicate?
And also Grey is an ideal line,can you please justify how is it?
Appreciate a quick response
Thanks,
Yogashree.M
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Red line explains how the Story points are actually burnt (in your case team hours)
Grey line is is ideal line for comparison with the Red line.
I dont see a Red line. Which version of JIRA Agile are you using