How can I have a different create issue screens for 2 projects?

Health Endeavors August 23, 2012

I seem to have it working on one project, but not on the other. The screen changes when I change the project, but it is not the screen I told it to use.

1 answer

0 votes
Jobin Kuruvilla [Adaptavist]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 23, 2012

Verify the screen schemes you use and amke sure it has the right issuetype screen schemes and screens.

Health Endeavors August 23, 2012

When I go to associate an issue operation with a screen, the create issue is not an option as it is already being used.

Health Endeavors August 23, 2012

ok, i think i got it worked out. thanks!

Suggest an answer

Log in or Sign up to answer