How Issues that were in status closed before closing the sprint can move to the next sprint?

עדי וקנין May 1, 2018

Hi,

I found 143 issues in the current active sprint that with status "Close". This status moved to status closed before I closed the previous sprint so how it possible that they moved to the current active sprint?

I filtered according to the next query: "Sprint=25 and  status = Closed AND status changed to Closed BEFORE startOfWeek() ".

For example (please see picture attached):

Closed issue move to the next sprint.png

1 answer

0 votes
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
May 1, 2018

What column were they in on the board when you ended the sprint?

עדי וקנין May 1, 2018

Hi,

What do you mean by column? those issues was in the section of sprint 5 before  I closed sprint 5. 

Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
May 1, 2018

Go to the board from which you created the sprint.  You'll see the issues grouped into columns.  I suspect your "section" means "column", but I am not sure.