Change default priority for a project

clsa November 16, 2020

Hello,

we are using Jira 7.1 right now.

Is it possible to change the default priority for a particular project? Under "Issues", I can only see "Priorities".

1 answer

1 accepted

1 vote
Answer accepted
Dirk Ronsmans
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
November 16, 2020

Hi @clsa ,

You could do this by creation a new priority scheme for that project.

If you go to "priority schemes" under your global administration:

https://hostname/secure/admin/ViewPrioritySchemes.jspa

you can create a new scheme, and associate it with that project. On your scheme you can set a default priority (which would then be applied for that project only)

 

image.png

clsa November 17, 2020

Hello @Dirk Ronsmans,

Thank you for your answer.

Unfortunately your mentioned link "https://hostname/secure/admin/ViewPrioritySchemes.jspa" doesn't work here:

screenshot.jpg

Is it a configuration issue or doesn't it just work under the version 7.1? I can only see see "Priorities":

screenshot.jpg

Dirk Ronsmans
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
November 17, 2020

Hi @clsa ,

Seems I indeed jumped the gun there. It appears to only be available from v7.6 and up.

https://www.atlassian.com/blog/jira-software/jira-software-server-7-6

Without scheme's I don't really see how to change the default one. Another way could be to use an automation/post function to set it at/after creation.. but then it's not really default, more changed to default :)

Prathmesh Mengane January 5, 2022

Hi @Dirk Ronsmans is the feature of Priorities schemes Not available on Standard Cloud edition? 

Dirk Ronsmans
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
January 5, 2022

@Prathmesh Mengane no indeed, priority schemes are not a feature on Cloud. (Any tier)

Ivo Stoyanov February 15, 2024

@Dirk Ronsmans hello, I'm not sure if I understand your last comment.

Do you mean we cannot create priority schemes in the Jira Service Management (Cloud) product?

Dirk Ronsmans
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
February 15, 2024

@Ivo Stoyanov ,

Correct! At this time you are not able to create priority schemes on Cloud. You will only have a single set of priorities that are used in all projects.
They are however working (and it is in EAP) on this feature for Cloud

 

https://community.atlassian.com/t5/Jira-Cloud-Admins-articles/Join-Atlassian-s-Early-Access-Program-for-Priorities-per-Project/ba-p/2454840

https://support.atlassian.com/jira-cloud-administration/docs/manage-priority-schemes/

 