Based on what Epic Burndown report considers a ticket as completed?

Alexander Zvonov
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 26, 2019

I have two green (Done) statuses in my workflow.  Closed and Accepted.  

Both have resolutions 'closed' and 'accepted' accordingly. 

If I close a ticket it appears in work completed section on Epic burndown.  But if I Accept the ticket it stays not completed. 

 

1.png3.png2.png

 

1 answer

0 votes
Alexander Zvonov
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 26, 2019

It turns out the only 'Closed' status can be considered as final staus to complete an issue.  Resolved , Accepted and any other in 'Done' category works as something intermediate