Hi,
I'm trying to populate a date custom field in JIRA through a groovy script using a date from a previous transition. I was trying to avoid SQL queries (even knowing that OS_HISTORYSTEP has the values that I want, specifically FINISH_DATE), and thought that ChangeHistoryManager would have what I need, but I don't see any methods to get the STEP_ID or ACTION_ID from ChangeHistories or ChangeItems. Since these are the ones I need for identifying my transition, is there any way to get them besides SQL? Or is there an easier way to do what I want?
(manually is not an option: there are 3000 issues in need of this)
Thank you!
Guilherme
Of course the are values you are looking for - look for changes of field status.
Have a look at TransitionsManager.java from JIRA Suite Utilities - although written rather obsolete way...
Well, that was pretty straightforward. Sometimes I forget that status is also a field...
Thank you very much!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.