When setting parent in plan restrict done epics from selection

Jenessa McRoy
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 10, 2023

When working in a plan in Jira, how do I restrict or hide done epics from being selectable as a parent? I also don't see a way to identify if an epic is done when it is in the parent list.

1 answer

0 votes
Marc - Devoteam
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 13, 2023

Hi @Jenessa McRoy 

Change the plan settings and set Done items view to 0 or empty, but this will mean for all issue types.

Or change the source of your plan, bas this upon a filter where you exclude Done Epics.

Show the status column in the plan, this can be done via the "fields" drop-down in the plan.