The Stories or the Tasks created as child issues under the EPICs are not apearing correctly underneath the epics on the timeline?
If I add a subtask under a story of Tasks it looks corect in the Timeline but not for epics
I need to be able to show top line projects then click into them to see the timeline of Stories/Tasks within the epics.
This is a team based project. I used the project management template as thats all we have access too.
Hi @victoria chaumeton and Welcome to the Atlassian Community!
it appears that nesting child issues under an Epic in the timeline view is not yet supported. Refer to;
https://jira.atlassian.com/browse/JWMCLOUD-111
Hope this helps. If the issue is resolved, you can vote and accepted for this comment.