Is there a way to see the percentage of completion of a plan on Jira?

Catarina Ferreira January 27, 2022

I have several plans on jira due to different countries I deal with and it´s great to manage it but I need to know the percentage of completion of this plan to see if I am on track or not and give status to management team. Is there a way to have that based on current plans created on Jira?

1 answer

1 vote
Vero Rivas
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 30, 2022
Catarina Ferreira February 1, 2022

Thank you Vero. What I would like is to see the percentage of an entire plan - not only epics separated. I would be like - I have 27 epics with some stories on each one, I would like to report that 15% of my plan is complete or 45% is complete based on all epics and stories completed. I was looking for a way to see and report that to management. 

Like Michael Staffa likes this
Tural Nabizade
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 24, 2024

Hi Catarina
I was now checking about this, and seems like Jira Plan now has a summary tab where from we can see the progress.

 

Summary Jira.jpg

Suggest an answer