In Jira BigPicture's resource modul, us it possible to change the workload individually?

Dorina Tóth
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 9, 2023

So we are planning to implement the BigPicture into a Pretty big company. When I see weekly working hours I can see that the work is equally shared between the planned weeks. Ex.: I have 3 weeks for the task which takes 30 hours to make, Jira now automatically allocated it to 10-10-10 hours per week. Now I know that the 50%of the work will be done on the 1st week, and than 10 and 5 will be worked on the task. How can I change it manually without having to create 3 indiviuals tasks for the 3 weeks. 

Thanks, in advance. 

2 answers

1 accepted

0 votes
Answer accepted
Marc - Devoteam
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 9, 2023

Hi @Dorina Tóth 

Welcome to the community.

You have reached the community form where the members are able to help you with questions in relation to Atlassian's products and in cases with marketplace app related topics.

You question is related to a specific function the does not exist in an app, we as the community can't tell you when this function will be there of will ever come.

For these type of questions is important to reach out to the developer of the app.

Dorina Tóth
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 9, 2023

Thank you for the quick answer.

0 votes
Béla Hegyesi October 11, 2023

Hi @Dorina Tóth

You are looking after the Manual workload contouring mode. According to my knowledge, it's a BigPicture Enterprise feature, but it's available. You can define under the Resources module, how would you like to distribute the estimated work. You can use front-loaded, back-loaded, or flat modes with a normal BigPicture subscription, and you can use the manual mode with an Enterprise subscription.
You can find more details in the documentation of BigPicture, here:
https://appfire.atlassian.net/wiki/spaces/DLP/pages/297046379/Workload+contouring 

Have a nice day!
Bela | EverIT