So we are planning to implement the BigPicture into a Pretty big company. When I see weekly working hours I can see that the work is equally shared between the planned weeks. Ex.: I have 3 weeks for the task which takes 30 hours to make, Jira now automatically allocated it to 10-10-10 hours per week. Now I know that the 50%of the work will be done on the 1st week, and than 10 and 5 will be worked on the task. How can I change it manually without having to create 3 indiviuals tasks for the 3 weeks.
Thanks, in advance.
Hi @Dorina Tóth
Welcome to the community.
You have reached the community form where the members are able to help you with questions in relation to Atlassian's products and in cases with marketplace app related topics.
You question is related to a specific function the does not exist in an app, we as the community can't tell you when this function will be there of will ever come.
For these type of questions is important to reach out to the developer of the app.
Thank you for the quick answer.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Dorina Tóth
You are looking after the Manual workload contouring mode. According to my knowledge, it's a BigPicture Enterprise feature, but it's available. You can define under the Resources module, how would you like to distribute the estimated work. You can use front-loaded, back-loaded, or flat modes with a normal BigPicture subscription, and you can use the manual mode with an Enterprise subscription.
You can find more details in the documentation of BigPicture, here:
https://appfire.atlassian.net/wiki/spaces/DLP/pages/297046379/Workload+contouring
Have a nice day!
Bela | EverIT