Tempo Planner - can you plan time by worklog attributes?

Is it possible to plan time to an issue and break it down by worklog attributes?

For example - our analyst will have a new development project that total has 70 hours for them. We break it down in the work log attributes by phase of work. Can I plan work for this BSA to one issue but by the specific hours per phase?

  • 25 hrs - Functional Documentation
  • 10 hrs - QA planning
  • 20 hrs - SIT Testing
  • 10 hrs - UAT Testing
  • 5 hrs - Post Production

2 answers

Hi Andrea,

this is not possible in the current version of Tempo Planner. The "smallest" unit you can plan time on is the JIRA issue. The worklog attributes are a Timesheets feature and can only be added to worklogs.

Regards,

Susanne

Hi,

This feature is missing in my mind. The opportunity to plan work and plan ressources to the good job.

A JIRA issue represents a sum of different work test, design, dev ...

 

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Bridget Sauer
Published Thursday in Marketplace Apps

Calling all developers––You're invited to Atlas Camp 2018

 Atlas Camp   is our developer event which will take place in Barcelona, Spain  from the 6th -7th of   September . This is a great opportunity to meet other developers and get n...

86 views 0 5
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you