Scrum and Kanban Board

Hello, 

Can you please answer these questions related to Scrum and Kanban Board?

1- Can we have a Scrum and Kanban Board for the same project which are visible to all JRIA Users? 

2- What is the easiest way to put all open JIRA Issues to active sprint window on the Scrum board?

Thank you.

1 answer

1 accepted

0 votes
Accepted answer
  1. Yes.  Just create and share two boards
  2. Go to the bottom of the list.  Click the last item so it is selected.  Scroll to the topof the list and use shift-click to select the whole lot.  Then drag into the sprint.

Nic, thanks a lot!

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Tuesday in Statuspage

Introducing Statuspage Getting Started guides! First up: What is Statuspage?

Over the next several weeks we'll be sharing some of our Getting Started guides here in the community. Throughout this series of posts, we'd love to hear from customers and non-customers ab...

244 views 4 1
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you