JIRA Porfolio question

Hello, I have a bunch of questions for JIRA Portfolio plugin. 

1. It is possible to have some of people to work on the weekends when building the schedules ?   

2. can I have two different holiday calendars (team is across two countries).

3: how can I make dependencies between issues so they are visible in Portfolio (like "start no earlier than another task finishes")

4. can I over allocate someone to lets say 45 hours for a week, while regular week is 40 hours.

5: can I export schedule so clients may get pdf .

6: can I assign someone to be working 50% of their time on task X and 40% of their time on task Y in the same week? how can I pick those ratios ? 

0 answers

Suggest an answer

Log in or Join to answer
Community showcase
Emilee Spencer
Published yesterday in Marketplace Apps

Marketplace Spotlight: DeepAffects

Hello Atlassian Community! My name is Emilee, and I’m a Product Marketing Manager for the Marketplace team. Starting with this post, I'm kicking off a monthly series of Spotlights to highlight Ma...

30 views 0 3
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot