we use original estimate field to populate the effort estimated for all tasks and sub-tasks. Is there a report to filter and get the work planned for next week in JIRA default reports?
It would be good to know more about what you are trying to do before jumping into an answer. Are you:
Thanks for the response.
I need a report which shows the work planned for the next week.
Example: I have a team of 3 people and they add tasks and sub tasks for the stories under their project. And all 3 of them work on different project and they have different release date to production. Under tasks and sub-tasks that they create they populate the original estimate. Is that information enough to create filter and get the report.
I am thinking I may have to add Due Date in all those tasks to get the actual work that needs to be done on any specific task. What do you suggest.
Is there any other simpler/better way to get this report.
Also, i found 'Time Tracking Report' under individual project which gives clear picture of what is the original estimate, remaining estimate, time spent and are we on track kind of information.
This report is driven based on the fix version field only. I am looking to get this report based on issue type for example: QA Task and QA Sub-Task. Is there a way I can get this report based on custom field? Is this configurable?
Please help. Help is much appreciated. Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.