Filter by "in progress" for a month period

Paul Dolton February 18, 2021

Hi

I have a client that wants to see all the tasks that have moved from to do ---> started / worked on / In progress for a 1 month period.

 

Can anyone advise me if this is possible?

1 answer

0 votes
John Funk
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
February 18, 2021

Hi Paul - Welcome to the Atlassian Community!

You can start with a filter like this: 

Project = ABC and status changed FROM "To Do" to "Started" AFTER startOfMonth()

That will show things that moved to started this month