Hey all, wish you good Friday! :)
İ have a simple question abuot tempo resource planning. I make team's plan for different projects. Can ı directly add this plan via excel or something else. Do ı have to spend my time for each day and each team member ?
King regards,
Burak Özkanlı
Hi, @Burak Özkanlı . Depending on the hosting type, you have 3 options:
It seems that you can import plans via 1) Excel (CSV) and via 2) Tempo's API too. This is valid for Jira Server:
You may also import plans from 3) Jira issues if each of the issues planned have an Assignee, a Due Date and Original Estimate. This is valid for Jira Cloud: Creating Plans from Jira issues (tempo.io).
There is also an open idea (feature suggestion) that you can vote for: Import plans to Tempo Planner using csv | Tempo Ideas.
Recommended Learning For You
Level up your skills with Atlassian learning
Learning Path
Jira Administrator
Configure Jira Software, Jira Core, or Jira Service Management, including global settings, permissions, and schemes.
Managing Jira Projects Cloud
Learn to create and configure company-managed projects in Jira Software and partner effectively with Jira Admins.
Learning Path
Become an effective Jira Software Project Admin
This learning path is designed for team leaders who configure Jira Software projects to match a team's processes.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.