Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in

Jira and Jira Align Integration: Sprint Best Practices

Before integrating Jira with Jira Align, there are some best practices that should be considered. Some are a little more rigid than others; while others can lend themselves to some workarounds. Let's explore further to understand what these are, why these are important and the potential impacts. 

 

Same sprint cadence for all teams in a program

All teams must have the same length sprints (1-week, 2-weeks, 3-weeks) within a program and must be consecutive.

Why: Anchor sprints (which team sprints roll up to) are generated by PI. Anchor sprints are used at the Program level for roll up of team data and sprints. This is needed to effectively plan and manage work across teams.

 

Sprints cannot be shared across boards

 

Sprints cannot be shared by multiple boards. Sprints also cannot be moved from one board to another.*

*For example, team decides to create a new board and retire their previous board and shares sprints to new board. Another example, team splits into two teams and sprints shared to new board.

Why: In Jira Align, it is only possible for sprints to belong to one team. The connector will associate sprints with the board from where the sprints were created. Team-level issues will sync over but will not be properly assigned to teams. Errors will be generated in the logs. In addition to cleaning up sprints, issues will need to be corrected as well.

Workaround: In the case where a team created a new board and using sprints from their old board, there is a setting (Sprints created and shared to board) that can be temporarily enabled to allow bringing in these sprints. The team must create sprints from the new board going forward.

Does not apply: Next Gen projects do not have the ability to have multiple boards per project.

 

Should not use “holding” or “bucket” sprints

Some teams will use “holding” or “bucket” sprints for stories that have been groomed and are ready for a sprint. This is not supported in Jira Align and this type of sprint must be ignored (if used).

Why: The connector cannot differentiate between true sprints and fake sprints.  Therefore, it will build these fake sprints into the team sprints in Jira Align creating misalignment of sprints. Corrective action needs to be taken when this happens.

Workaround: If a fake sprint is used, it must be ignored in the connector. Reuse the same one PI over PI and just rename it if needed. If new ones are created, they will need to be ignored in the connector. If creating new ones, Admin will need to be informed to ignore sprint in connector.

General Best Practice (not specific to integration): Sprints should represent work to be done within a certain time box. Use statuses instead of bucket sprints to represent groomed stories.

Product Managers should not be placing holding work for teams as this does not foster agile practices.

Does not apply: Not an issue for Data Center.

 

Enter sprint dates and don’t overlap start and end dates

Set sprint dates ahead of time with unique start and end dates. If using the Start Sprint option to generate dates, make sure the start date is the the first date of the sprint when starting the sprint. 

Why: Jira Align doesn’t recognize time stamps that can be set/generated in Jira; only the dates. Overlapping of start and end dates could result in inaccurate mapping.

When using the the Start Sprint option to generate dates on sprints, the start date defaults to “today’s” date. If the sprint is started for some reason after the first date of the sprint, this needs to be adjusted. When selecting “weeks” options as the Duration, it will cause the last date of the current sprint to overlap with the first date of the next sprint. The custom option allows for appropriate setting of the end date.

 

Only one active team sprint

There should only be one active sprint at a time per board.  Future planning sprints are acceptable. There is a setting in Jira that can prevent having two active sprints.

Why: The connector uses the active sprint in Jira to build future sprints in Jira Align. If there are multiple active sprints, the sprints may become out of sync in Jira Align and corrective action will need to be taken.

General Best Practice (not specific to integration): Team velocity can become inaccurate when multiple sprints are active at the same time.

 

Create and manage sprints in Jira

Sprints should be created and managed in Jira. Management includes any changes such as the name, starting and completing sprints.

Why: Sprints sync unidirectionally from Jira to Jira Align.  Sprints created in Jira Align will not sync to Jira.  Sprints started or completed in Jira Align will not sync to Jira.  Updates made to sprint names in Jira Align will not sync to Jira.

If there is a desire to create team IP sprints in Jira Align, these are not treated any differently in reporting in Jira Align and there would be no value in this action.

 

Addressing Stories not completed in an Active Sprint in Jira

Stories that are not completed should be moved out of the Sprint prior to the Complete Sprint Action.  When Stories are moved to a Future Sprint or moved to the Backlog during the Complete Sprint Action they will retain the original Sprint.  

Why: Jira Align only recognizes a single sprint on any work item, when multiple sprints exist on that item Jira Align will not always select the appropriate Sprint to map the work to and data will be inaccurate. 

The action to remove the story from the sprint can be taken from the Active Sprint view or the Backlog view. 

  • Active Sprint View:  Right click on the card and select "Remove from Sprint", this will clear the sprint value and send the story to the Backlog. 
  • Backlog View:  Right click on the card and select either the "Top of Backlog" or "Bottom of Backlog".  Additionally you can use the Drag and Drop method to move the story to the Backlog.  
    • Note:  In the Backlog View, Jira will also clear the Sprint value from the story if it is dragged to a Future Sprint. 

Do not change order of sprints on Jira board or delete them

Once sprints have been created on the Jira board and synced to Jira Align, they need to remain in the order they were created.

Why: If sprints are rearranged (dragged and dropped after sprints have been synced) or deleted, it can cause the sprints to be out of sync b/w Jira and Jira Align. If this is done, manual corrective action will need to be taken.

It’s better to rename sprints than to delete or move.

 

Cannot use parallel sprints

Cannot use parallel sprints to divide work between regression and enhancement work sprints. (Other examples are division of QA and dev and delay with PO accepting stories.)

Why: If selected, it is not possible for the connector to determine which one to sync because it will generate two active sprints. When the second sprint closes, it will create a syncing issue.

Setting is not project specific and is whole instance.

Related article: Cloud: Use parallel sprints

 

Integration behaviors to be aware of

  • Depending on where the servers are located for Jira Align and Jira, this could cause a difference between applying sprint dates
  • Jira Align reads team sprint dates for items on the Program Board that are not aligned with the anchor sprints displayed in the Sprints column headers. This can result in false scheduling issues.

 


Related Articles

4 comments

Matt Rosenbluth
Contributor
November 22, 2023

Hi @Rae Gibbs Is it allowed for PIs to be set up like this?
Sprint 1-5 - 2 weeks

Sprint 6 - 2 weeks (IP sprint + working time)

Sprint 7 - 1 weeks (IP sprint)

My inclination is to require the sprints to follow the 2-week structure, leaving the IP sprint at the end.

Additionally, is it still an issue with velocity and IP sprints: https://jira.atlassian.com/browse/JIRAALIGN-1282

Thanks,

Matt

Isaac Greenberg March 1, 2024

Just wanted to say this is a great guide.  Thanks!

Alan Williams
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 17, 2024

@Rae Gibbs - Can we use the "generate sprints" button in Jira Align to push sprints down into the connected team boards in Jira?

Rae Gibbs
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
September 17, 2024

@Alan Williams No, it is not possible to push sprints from JA to Jira. The synchronization of sprints is only support one way from Jira to JA. All creation and management of sprints MUST be done in Jira.

Comment

Log in or Sign up to comment
TAGS
AUG Leaders

Atlassian Community Events